Questions

Q:

A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?

A) Project integration plan. B) WBS development plan.
C) Configuration management plan. D) Scope management plan.
 
Answer & Explanation Answer: D) Scope management plan.

Explanation:

“The work involved in performing the five processes of Project Scope Management is preceded by a planning effort by the project management team. This planning effort is part of the Develop Project Management Plan process, which produces a scope management plan that provides guidance on how project scope will be defined, documented, verified, managed, and controlled. The scope management plan may be formal or informal, highly detailed, or broadly framed, based upon the needs of the project.”

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

2 5257
Q:

Which is the folk dance of Andhra Pradesh?

A) Kolattam B) Karakattam
C) Lavani D) Saturi
 
Answer & Explanation Answer: A) Kolattam

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian Culture

62 5256
Q:

What command is used to count the total number of lines, words, and characters contained in a file ?

A) wc B) count p
C) wcount D) countw
 
Answer & Explanation Answer: A) wc

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Computer
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Bank Clerk , Bank PO

15 5256
Q:

Online functional learning portals are accessed through the

A) Web portal B) Interactive Multimedia Instruction
C) Instructor Facilitated New Equipment D) All the above
 
Answer & Explanation Answer: A) Web portal

Explanation:

Online functional learning portals are accessed through the web portal.

Report Error

View Answer Report Error Discuss

Filed Under: Computer
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank Clerk , Bank PO

8 5255
Q:

One method by which the components of air can be seperated is 

A) shaking with caustic soda solution B) shaking with water
C) fractional distillation of liquid air D) passing air over heated magnesium
 
Answer & Explanation Answer: C) fractional distillation of liquid air

Explanation:

The two main components of air are nitrogen and oxygen. They are seperated by the fractional distillation of liquid air. Liquefied air contains liquid nitrogen and liquid oxygen. Liquid nitrogen with the lower boiling point more readily evaporates than the less volatile liquid oxygen. 

Report Error

View Answer Report Error Discuss

Filed Under: Chemistry

6 5254
Q:

The God who is the most prominent in ' Rigaveda 'is

A) Indra B) Agni
C) Pasupati D) Vishnu
 
Answer & Explanation Answer: A) Indra

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Indian History

2 5253
Q:

'The Peloponnesian war' was fought between _______ and _____

A) Sparta and Iran B) Sparta and Athens
C) Athens and Iran D) Athens and Asia Minor
 
Answer & Explanation Answer: B) Sparta and Athens

Explanation:

The Peloponnesian war, between Athens and Sparta from 431 to 404 BC ended in the defeat of Athens and the destruction of her democracy. Athens became a subject state of sparta. This war marked the beginning of the end of the "Glory that was Greece".

Report Error

View Answer Report Error Discuss

Filed Under: World History

9 5252
Q:

Which of the following is not an aerosol?

A) mud B) dust
C) smoke D) fog
 
Answer & Explanation Answer: A) mud

Explanation:

Among the given options, mud is not an aerosol.

 

An aerosol is a suspension of fine solid particles or liquid droplets, in the air or another gas. Aerosols can be natural or anthropogenic. Examples of natural aerosols are fog, dust, forest exudates and geyser steam. Examples of anthropogenic aerosols are haze, particulate air pollutants, and smoke.

Report Error

View Answer Report Error Discuss

Filed Under: Physics
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO , IT Trainer

5 5252