Questions

Q:

Which Bank has opened 9 SmartUp Zones in Bengaluru, Karnataka?

A) Axis Bank B) SBI Bank
C) Karnataka Bank D) HDFC Bank
 
Answer & Explanation Answer: D) HDFC Bank

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: Bank Exams , CAT
Job Role: Bank Clerk

5 3536
Q:

What type of Lipid is Estrogen?

A) phospholipid B) steroid
C) wax D) triglyceride
 
Answer & Explanation Answer: B) steroid

Explanation:

Estrogen is a group of steroid hormone that control the development and maintenance of an individuals feminine characteristics. Natural estrogen exists in men as well as women and are found in higher amounts in women Especially in those of reproductive age.

 

Estrogens are hormones which are responsible to the body functions of the female body system such as menstruation, development of the female body such as pubic hair, breasts and development of the proportions of the body.

 

Lipids act as best energy storage molecules as the cleavage of fatty acids produces both energy and metabolic water which is a main component in almost all lipids.

Report Error

View Answer Report Error Discuss

Filed Under: Chemistry
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank Clerk , Bank PO , IT Trainer

1 3535
Q:

Cortisol is secreted by

A) Thyroid gland B) Pituitary gland
C) Adrenal gland D) Parathyroid gland
 
Answer & Explanation Answer: C) Adrenal gland

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Biology

6 3535
Q:

Which of the following elements is a metalloid?

A) arsenic B) boron
C) antimony D) All of the above
 
Answer & Explanation Answer: D) All of the above

Explanation:

A metalloid is any chemical element which has properties in between those of metals and nonmetals, or that has a mixture of them.

The six commonly recognised metalloids are

boron,

silicon,

germanium,

arsenic,

antimony, and

tellurium.

Report Error

View Answer Report Error Discuss

Filed Under: Chemistry
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO

3 3535
Q:

The primary effect on climate of a volcanic eruption depends on______

A) the quantity of lava produced B) how hot the eruptive products are
C) the amount of water vapour produced D) none of the above
 
Answer & Explanation Answer: D) none of the above

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: World Geography

2 3535
Q:

Bob Kashir deposited $6000 in a 4-year certificate of deposite paying 5% compounded daily.He withdrew the money 15 months later.The passbook rate at his bank is 3.5 % compounded daily.Find his amount of interest

A) 5678 B) 4563
C) 4329 D) 6210.73
 
Answer & Explanation Answer: D) 6210.73

Explanation:

Bob receives 15-3 = 12 months of 3.5 % interest compounded daily

 

 

 

M=P(1+i/365)^365n

Report Error

View Answer Report Error Discuss

0 3534
Q:

Which of the following is the largest non-banking company in India?

A) Peerless B) Tata Finance
C) Reliance Finance Capital Ltd D) ICICI
 
Answer & Explanation Answer: D) ICICI

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Business Awareness

14 3534
Q:

The project life cycle can be broken into five phases that tend to overlap with each other frm one phase to another;however ,the control phase does not overlap with a specific phase. why?

A) Change control management is seperate from the other phases B) Change control management has a plan that can be usede throughout the initiation, planning, execution, and closeout of the project
C) Because the project sponsor is responsible for change control management , the project manager is not involved with that phase of the project D) Change control extends throughout the entire project from initiation to closeout
 
Answer & Explanation Answer: D) Change control extends throughout the entire project from initiation to closeout

Explanation:

Change control management is utilized from the begining to the end of the project in order to keep it focused with an emphasis on the time and budget. Answer A is incorrect because change control management is not seperate from the other phases. Answer B is incorrect because the control plan must be throughout the other phases of a project. Its usage is not optional, and consistent utilization is imperative to managing scope creep and other scope expansions. Answer C is incorrect because the project sponsors is generally not responsible for the change control documentation, although it should be involved in the buy-in and approval process.