Q:

A, B and C can do a piece of work in 72, 48 and 36 days respectively. For first p/2 days, A & B work together and for next ((p+6))/3days all three worked together. Remaining 125/3% of work is completed by D in 10 days. If C & D worked together for p day then, what portion of work will be remained?

A) 1/5 B) 1/6
C) 1/7 D) 1/8
 
Answer & Explanation Answer: B) 1/6

Explanation:

Total work is given by L.C.M of 72, 48, 36

Total work = 144 units

Efficieny of A = 144/72 = 2 units/day

Efficieny of B = 144/48 = 3 units/day

Efficieny of C = 144/36 = 4 units/day

 

According to the given data,

2 x p/2 + 3 x p/2 + 2 x (p+6)/3 + 3 x (p+6)/3 + 4 x (p+6)/3 = 144 x (100 - 125/3) x 1/100

3p + 4.5p + 2p + 3p + 4p = 84 x 3 - 54

p = 198/16.5

p = 12 days.

 

Now, efficency of D = (144 x 125/3 x 1/100)/10 = 6 unit/day

(C+D) in p days = (4 + 6) x 12 = 120 unit

Remained part of work = (144-120)/144 = 1/6.

Report Error

View Answer Report Error Discuss

7 8267
Q:

How many balls?

Number of balls in the figure...

balls1523099634.jpg image

Answer

You have to actually count all the balls in the pyramid.
Simple way is to count the balls in each level.


So lower most level lets say 1st level has 4 x 4 balls; i.e. 16 balls
Similarly 2nd level has 3 x 3 balls; i.e. 9 balls.
3rd level has 2 x 2 balls; i.e. 4 balls.
The top most level has just 1 ball.


So the total number of balls is 16+9+4+1 = 30.


 


So the image has 30 Balls in all.

Report Error

View answer Workspace Report Error Discuss

11 8262
Q:

How to call a constructor in java?

Answer

Constructor chaining is the process of calling one constructor from another constructor with respect to current object.





Within same class: It can be done using this() keyword for constructors in same class


From base class: by using super() keyword to call constructor from the base class.

Report Error

View answer Workspace Report Error Discuss

10 8228
Q:

Planet : Orbit :: Projectile : ?

A) Path B) Milky way
C) Track D) Trajectory
 
Answer & Explanation Answer: D) Trajectory

Explanation:

The path traced by planet is called Orbit. Similarly, the path traced by projectile is called Trajectory.

 

Hence, Planet : Orbit : : Projectile : Trajectory.

Report Error

View Answer Report Error Discuss

Filed Under: Analogy
Exam Prep: AIEEE , Bank Exams , CAT , GATE , GRE , TOEFL
Job Role: Analyst , Bank Clerk , Bank PO , Database Administration , IT Trainer

8 8204
Q:

Two letters are randomly chosen from the word TIME. Find the probability that the letters are T and M?

A) 1/4 B) 1/6
C) 1/8 D) 4
 
Answer & Explanation Answer: B) 1/6

Explanation:

Required probability is given by P(E) = n(E)n(S) = 14C2 = 16

Report Error

View Answer Report Error Discuss

20 8117
Q:

What kind of apple isn't an apple?

A) Pineapple B) Akero apple
C) Adanac apple D) Aceymac apple
 
Answer & Explanation Answer: A) Pineapple

Explanation:

Except pineapple remaining all three are types of apples.

Pineapple is what kind of apple isn't an apple.

Report Error

View Answer Report Error Discuss

Filed Under: Logic Puzzles
Exam Prep: AIEEE , Bank Exams , CAT , GATE , GRE
Job Role: Analyst , Bank Clerk , Bank PO , IT Trainer

4 8099
Q:

Rushi and Arun are two business partners. They invest their capital in the ratio 7 : 9. After 6 months, a third person Ram joins them with a capital of two third of that of Arun. After a year, profit share of Rushi was Rs. 5600, then find total profit?

A) 26,250 B) 19,200
C) 18,650, D) 15,200
 
Answer & Explanation Answer: D) 15,200

Explanation:

Ratio of investment of all the three members = (7 x 12) : (9 x 12) : (2/3 x 9 x 6)

= 7 : 9 : 3

Given Rushi's one year profit = Rs. 5600

=> Let the total profit = Rs. P

Then,

P x 7/19 = 5600

Total profit P = 19 x 5600/7 = Rs. 15,200.

Report Error

View Answer Report Error Discuss

Filed Under: Partnership
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO , IT Trainer

8 8036
Q:

Central processing unit is combination of

A) Arithmetic and Control unit B) Control and Output unit
C) Control and Storage unit D) Arithmetic logic and input unit
 
Answer & Explanation Answer: A) Arithmetic and Control unit

Explanation:
Report Error

View Answer Report Error Discuss

9 8026