Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Develop project management plan phase?

Answer

I. Inputs



  • Preliminary project scope statement

  • Project management processes

  • Enterprise environmental factors

  • Organizational process assets


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Project management plan

Report Error

View answer Workspace Report Error Discuss

0 2186
Q:

What is process synchronization?

Answer

A situation, where several processes access and manipulate the same data concurrently and the outcome of the execution depends on the particular order in which the access takes place, is called race condition. To guard against the race condition we need to ensure that only one process at a time can be manipulating the same data. The technique we use for this is called process synchronization.

Report Error

View answer Workspace Report Error Discuss

1 2186
Q:

The island of Sri Lanka formerly known as

A) Maldives B) Bali
C) Ceylon D) Madagaskar
 
Answer & Explanation Answer: C) Ceylon

Explanation:

In the history, at the time of British rule in 1800's, the island of Sri Lanka formerly known as Ceylon. It is a south asian country located in the northest of the indian ocean.

the_island_of_sri_lanka_formerly_known_as1553080594.png image

Report Error

View Answer Report Error Discuss

Filed Under: World History
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

0 2186
Q:

Where's MBR located on the disk?

Answer

Main Boot Record is located is sector 0, track 0, head 0, cylinder 0 of the primary active partition.

Report Error

View answer Workspace Report Error Discuss

Subject: Hardware

0 2185
Q:

ABC is right angled at B. BD is an altitude. AD = 4 cm and DC = 9 cm. What is the value of BD (in cm)?

A) 5 B) 4.5
C) 5.5 D) 6
 
Answer & Explanation Answer: D) 6

Explanation:
Report Error

View Answer Report Error Discuss

0 2185
Q:

Project Cost Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Cost Budgeting ?

Answer

I. Inputs



  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Activity cost estimates

  • Activity cost estimate supporting detail

  • Project schedule 

  • Resource calendars 

  • Contract

  • Cost management plan


II. Tools and Techniques



  • Cost aggregation

  • Reserve analysis

  • Parametric estimating 

  • Funding limit reconciliation


III. Outputs



  • Cost baseline 

  • Project funding requirements 

  • Cost management plan (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 2185
Q:

Read the passage carefully and choose the best answer to each question out of the four alternatives and click the button corresponding to it.


There is a time in every man's education when he arrives at the conviction that envy is ignorance; that imitation is suicide; that he must take himself for better, for worse, as his portion; that though the wide universe is full of good, no kernel of nourishing corn can come to him but through his toil bestowed on that plot of ground which is given to him to till. The power which resides in him is new in nature, and none but he knows what that is which he can do, nor does he know until he has tried. Not for nothing one face, one character, one fact, makes much impression on him, and another none. This sculpture in the memory is not without pre-established harmony. The eye was placed where one ray should fall, that it might testify of that particular ray. We but half express ourselves, and are ashamed of that divine idea which each of us represents. It may be safely trusted as proportionate and of good issues, so it be faithfully imparted, but God will not have his work made manifest by cowards. A man is relieved and gay when he has put his heart into his work and has done his best; but what he has said or done otherwise, shall give him no peace. It is a deliverance which does not deliver. In the attempt his genius deserts him; no muse befriends; no invention, no hope.

 

According to the author, God is not looking for _____ to manifest his works.

A) Cowards B) Stubborn people
C) Weaklings D) All of these
 
Answer & Explanation Answer: A) Cowards

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 2185
Q:

Which work of art uses hierarchical scale?

A) painting B) sculpture
C) both a & b D) none
 
Answer & Explanation Answer: C) both a & b

Explanation:

Hierarchical scale is used in both painting and sculpture works of arts.

Report Error

View Answer Report Error Discuss

Filed Under: General Science
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

1 2185