Q:

In an objective competitive exam, a correct answer score 4 marks and on a wrong answer 2 marks are negatively added. A student scores 420 marks from 150 question. How many answers were correct ?

A) 145 B) 138
C) 125 D) 120
 
Answer & Explanation Answer: D) 120

Explanation:

let x be the correct answer and y be the wrong answer
so the total number of questions is (x + y) = 150.....(1)
=> 4x - 2y = 420.....(2)
By solving (1) & (2), we get
=> 6x = 720
hence x = 120
Therefore, number of correct answers are 120.

Report Error

View Answer Report Error Discuss

Filed Under: Logic
Exam Prep: AIEEE , Bank Exams , CAT , GATE , GRE
Job Role: Analyst , Bank Clerk , Bank PO

Q:

A group of six cousins are sitting around a hexagonal table, each one at one corner of the hexagon. (facing the centre inside) Raju is sitting opposite to Rohan. Sweety is sitting next to Navya. Aadya is sitting opposite to Navya, but not next to Kalyan. Karthik has a person sitting between Rohan and himself. If Sweety sits to the right of Karthik, then who is sitting to the left of Karthik ?

A) Aadya B) Kalyan
C) Raju D) Rohan
 
Answer & Explanation Answer: C) Raju

Explanation:

Suppose Sweety is sitting between Rohan and Karthik such that she is to the right of him.....then as Raju is opposite to Rohan then Raju must be to the left of Karthik.

Report Error

View Answer Report Error Discuss

Filed Under: Logic
Exam Prep: AIEEE , Bank Exams , CAT , GATE , GRE
Job Role: Analyst , Bank Clerk , Bank PO

Q:

How many meshes are there in 1 squrare meter of wire gauge if each mesh is 8mm long and 5mm wide ?

A) 2500 B) 25000
C) 12500 D) 15400
 
Answer & Explanation Answer: B) 25000

Explanation:

We know that,

 

One square meter is equal to 10,00,000 sq mm.
Given, each mesh is 8mm length and 5mm wide
Therefore for each mesh : 8 x 5 = 40 sq mm.
So, number of meshes = 100000040 = 25000.

Report Error

View Answer Report Error Discuss

Filed Under: Volume and Surface Area
Exam Prep: GRE , GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst

Q:

19 persons do 19 programs in 19 hours . If they take 15 mins interval and then how much time they need to do 52 programs.

A) 23 hours B) 47 hrs 15 min
C) 52 hrs 15 min D) 22 hrs 15 min
 
Answer & Explanation Answer: C) 52 hrs 15 min

Explanation:

Since they can do 19 programs in 19 hours, Then 52 programs in 52 hours respectively.
And a 15 min interval
Total time they take to do 52 programs is 52 hours 15 minutes.

Report Error

View Answer Report Error Discuss

Q:

A 300m race is held between two players running 3m/s and 5m/s in swimming pool of 50m long. how many times the two player meet in opposite direction till the faster one completes the race ?

A) 3 times B) 4 times
C) 5 times D) 2 times
 
Answer & Explanation Answer: A) 3 times

Explanation:

Let us assume A is the faster and B is slower, A takes 10s to finish a lap of 50 m, B takes 17s(approx) to finish a lap of 50 m.
So at 11th sec A starts his 2nd lap by the time B will be in between so that is the first time they will meet each other, at 21st sec A starts his 3rd lap by the time B will be coming back to finish his 2nd lap. So that is the second time they meet in opposite. Then at 31st sec A will start his 4th lap by the time B would not even finish 2nd lap as he take 34(2*17) sec to finish 2 laps. So at 35th sec B will start his 3rd lap by the time A will be coming back to finish his 4th lap in the half way so they will meet 3rd time. At 41st sec A will start its fifth lap by the time B will be going to finish 3rd lap in same direction. At 50th second both will complete A's 5th lap and B's 3rd lap. So they will start next lap(A's 6th and B's 4th) from the same point in same direction. And A will finish the race after completing 300m(6*50) total distance and then they wont meet opposite to each other.

So totally they met 3 times in opposite direction.

Report Error

View Answer Report Error Discuss

Filed Under: Logic
Exam Prep: AIEEE , Bank Exams , CAT , GATE , GRE , TOEFL
Job Role: Analyst , Bank Clerk , Bank PO

Q:

The ratio between the number of sheep and the number of horses at the Stewar farm is 4 to 15. If each of horse is fed 110 ounces of horse food per day and the farm needs a total 13200 ounces of horse food per day. what is number sheep in the form ?

A) 32 B) 36
C) 44 D) 52
 
Answer & Explanation Answer: A) 32

Explanation:

Given ratio of number of sheep and horses = 4 : 15
Let number of sheep and horses are 4k and 15k
Number of horses = 13200/110 = 120
Now 15K = 120 and k = 8
Number of sheep = 4k = (4 x 8) = 32

Report Error

View Answer Report Error Discuss

Filed Under: Ratios and Proportions
Exam Prep: AIEEE , Bank Exams , CAT , GATE , GRE
Job Role: Analyst , Bank Clerk , Bank PO

Q:

The difference between two numbers is 3355. When the larger number is divided by the smaller one, the quotient is 6 and the remainder is 15. The smaller number and larger number respectively ?

A) 546, 3901 B) 415, 3770
C) 668, 4023 D) 404, 3759
 
Answer & Explanation Answer: C) 668, 4023

Explanation:

Let the smaller number be k.
Then, larger number = (3355 + k)
Therefore 3355 + k = (6k + 15)
‹=› 5k = 3340
‹=› k = 668.

Therefore, the smaller number k = 668 and now the larger number = 3355+668 = 4023.

Report Error

View Answer Report Error Discuss

Q:

K, L and M can do a piece of work in 20, 30 and 60 days respectively. In how many days can K do the total work if he is assisted by L and M on every third day ?

A) 15 days B) 13 days
C) 12 days D) 10 days
 
Answer & Explanation Answer: A) 15 days

Explanation:

In one day work done by K = 1/20

Work done by K in 2 days = 1/10

 

Work done by K,L,M on 3rd day =1/20 + 1/30 + 1/60 = 1/10

Therefore, workdone in 3 days is = 1/10 + 1/10 = 1/5

 

1/5th of the work will be completed at the end of 3 days.

The remaining work = 1 - 1/5 = 4/5

1/5 of work is completed in 3 days

Total work wiil be done in 3 x 5 = 15 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GRE , GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk , Analyst