Q:

Iam looking to estimate the cost on a project, but I don't want to spend a lot of time on a  detailed analysis. I really want a ballpark figure. What options do I have?

A) None - Cost estimating requires details to be accurate B) Use the cost of similar projects
C) Use a rule-of-thumb or per-square-foot estimate D) Add up the costs on the WBS
 
Answer & Explanation Answer: B) Use the cost of similar projects

Explanation:

Although it is less accurate than adding up individual costs from the WBS, it is less time consuming. The trade-off is accuracy. Answer A is incorrect because to do a more accurate cost estimate, you need to delve into details. Answer C is tempting also, and possible, except we don't really know if the project in question can use perametric modeling . Answer D is incorrect because it takes the most time, but it is most accurate.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

On a systems development project, Richard needs two programmers. He knows John and Smith were able to create a program in 40 days similar to the one he wants to create on his project. He decides to use 40 days as his estimate. This is an example of what type of estimating?

A) Parametric modeling B) Analogous
C) Rule of thumb D) Fixed Rate
 
Answer & Explanation Answer: B) Analogous

Explanation:

Richard is using an estimate based on a project very similar to to his own with staff he will be using.  Answer A is incorrect because perametric modeling involves using a mathematical model to predict costs, such as dollars per line of code. Answer C is incorrect, although close; if the development project is a common item, such as putting down new flooring, a rule -of-thumb measurement can be used, although it is less accurate. Answer D is incorrect because it is not a form of estimating, but a type of pricing.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

Your company has a policy of having every software project reviewed and approved by the Architecture Review Board prior to the construction  phase of a project. you are currently in the process of activity sequencing. This is a example of what?

A) Gatekeeping B) Milestone
C) New scope for the project D) Project integration
 
Answer & Explanation Answer: B) Milestone

Explanation:

The approval by the Architecture Review Board is a milestone you want to include in activity sequencing so that you can ensure the requirements for meeting the review board's approval are met.  Answer A is tempting because the question references phase-end activities; however, it is not an example of gatekeeping because the project is not being authorized to continue based only on the architecture review.Gatekeeping often involves the review of other factors as well. Answer C is incorect because the requirement of a review board approval does not afect scope. Answer D is incorrect because project integration planning involves project plan development, execution, and integrated change control, which are not related to a review board.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

You are working on a new project to develop a new wireless product with ease - of - use features recommended by customers. It is as yet undetermined which features and the extent to which each feature will be incorporated into the product.You have a focus group that will continue to evaluate the features as the project goes forward.The focus group is authorized to suggest changes, as are your engineers and the quality department.As a project manager, what will help you most to minimize the effect of these changes?

A) A change management plan B) A scope management plan
C) Do not continue with the project until all of the features are clearly defined in the scope statement and scope definition. D) This is an expected part of every project. A good project manager will have a communications plan in place to be sure everyone knows what is happening on the project.
 
Answer & Explanation Answer: B) A scope management plan

Explanation:

Answer A is tempting because the problem focuses on changes. However, because we are talking about the elaboration of the product's characteristics, we are talking about scope changes, and therefore Answer B is the best answer. Answer C is also tempting because it is difficult to more forward on a project until the scope is clearly defined (especially in systems development projects), but with products and certain types of web development, scope changes can be frequent, and a formal scope management plan is needed. Answer D is true from a project perspective, but does not addres the scope issues.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

A Good CFO will tell you that it is important to look at your bottom line and determine how to increase profits for the organization. Veronica, the new CFO at a local university, is taking that approach and applying it to new projects. Therefore,she wants to include costs from each phase of the project on a total expenditure is known as 

A) An opportunity cost B) A sunk cost
C) NPV D) A life cycle
 
Answer & Explanation Answer: D) A life cycle

Explanation:

Life Cycle costing includes the costs from each phase of the project life cycle when the total investment costs are calculated. Answer A is incorrect because an opportunity cost is the difference between a chosen investment and the one that is passed up. Answer B is incorrect because sunk costs are costs that have been incurred and cannot be reversed. Answer C is incorrect because net present value (NPV) is the present value of cash inflows(benifits) minus the present value of cash outflows (costs).

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

Subject matters experts (SMEs) are resources that are imperative to the succes of a project. Many times, project managers are not experts in the areas they are managing and frequently must rely upon other's expertise. In which scope - management process are SMEs first used?

A) Scope planning B) Scope definition
C) Initiation D) Scope verification
 
Answer & Explanation Answer: C) Initiation

Explanation:

Initiation is the first step in the scope management process, and expert judgment is one of the techniques routinely utilized. Answers A, B, and D are incorrect because they would come after the initiation process.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

Project authorization is one of the processes that is associated with the initiation phase of a project. Authorization can come in many different forms, and projects are generally authorized by all of the following except

A) Technological Advances B) Customer request or market demand
C) Executive year - end bonuses D) Business or Social needs
 
Answer & Explanation Answer: C) Executive year - end bonuses

Explanation:

Project authorization should not be exclusively based upon the impact of an executive's bonus (many people would agree that it should not ever be based upon an executive's bonus). Answer A, B, and D are common events that predicate the need for project authorization and can evolve into large scope projects.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

The payback period can become an important issue when a large scope project is developed over several years. Maureen has been assigned the responsibility of calculating the payback period for her project that is to be completede in 3 years. The internal rate of return(IRR) is 7% and the annual savings will be $800,000 per year. The total cost is $4,000,000 and the rate of return during this time period is 3%. What is the payback period of Maureen's project?

A) 3 years B) 4 years
C) 5 years D) 13.3 years
 
Answer & Explanation Answer: C) 5 years

Explanation:

The payback period is how long it takes to recoup your investment. In this example, the cost was $4,000,000 and the savings was $800,000 per year. $4,000,000/$800,000 = 5. Therefore, Answer A, B and D are incorrect.

Report Error

View Answer Report Error Discuss