Q:
| A) An opportunity cost | B) A sunk cost |
| C) NPV | D) A life cycle |
Answer: D) A life cycle
Explanation:
Explanation:
Life Cycle costing includes the costs from each phase of the project life cycle when the total investment costs are calculated. Answer A is incorrect because an opportunity cost is the difference between a chosen investment and the one that is passed up. Answer B is incorrect because sunk costs are costs that have been incurred and cannot be reversed. Answer C is incorrect because net present value (NPV) is the present value of cash inflows(benifits) minus the present value of cash outflows (costs).