Q:

The organizational form in which the project manager has informal authority over team members and little or no input to team member’s performance appraisal is called

A) weak matrix. B) functional.
C) strong matrix. D) composite.
 
Answer & Explanation Answer: A) weak matrix.

Explanation:

“Weak matrices maintain many of the characteristics of a functional organization, and the project manager role is more that of a coordinator or expediter than that of a true project manager.”

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

Report Performance is a member of which process group?

A) Controlling B) Planning
C) Executing D) Closing
 
Answer & Explanation Answer: A) Controlling

Explanation:

The processes in the controlling group are Verify Scope, Control Scope, Control Schedule, Control Costs, Perform Quality Control, Report Performance, Monitor and Control Risks, and Administer Procurements.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

George is very open with his team members. He invites questions and discussion, and encourages new suggestions and ideas. He considers all this carefully before making any but the most minor project decisions, but ultimately chooses the course he personally believes is the right one. His leadership style is best characterized as

A) Democratic B) Consultative
C) Participative D) Benevolent
 
Answer & Explanation Answer: C) Participative

Explanation:

The Participative leadership style is characterized by 1) allowing a great deal of freedom in identifying problems and solutions, 2) working closely with subordinates, 3) allows extensive participation, but 4) reserving to him/herself the final decision. The consultative style is not so open, with discussion more focused around the leader’s uncertainties than asking for new ideas.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

Activities done repeatedly over time will become more efficient, increase in quality and will be found to be less demanding by the performing people. This is known as the

A) Learning Curve Theory. B) Continuous Improvement Theory.
C) Six-sigma Theory. D) Homeostasis Theory.
 
Answer & Explanation Answer: A) Learning Curve Theory.

Explanation:

Answers B and C belong to quality management, and answer D was formulated by Elizabeth Duffy and suggested that we all try to adjust our lives so that we have a dynamic balance (homeostasis) between challenge and relaxation. Kerstner, Chapter 18

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

The schedule performance index (SPI) is calculated as

A) Planned Value (PV) divided by Earned Value (EV) B) Earned Value(EV) divided by Planned Value (PV)
C) Project duration divided by Earned Value divided by Planned Value (Duration/(EV/PV)) D) Earned Value (EV) minus Planned Value (PV)
 
Answer & Explanation Answer: B) Earned Value(EV) divided by Planned Value (PV)

Explanation:

Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it’s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance. 

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

Which of the following is usually not considered a goal of portfolio management?

A) To manage the effective and efficient use of resources. B) To balance the portfolio among incremental and radical investments.
C) To maximize the value of the portfolio by careful examination of candidate projects and exclusion of those no meeting strategic objectives. D) To ensure that the relationship between projects in the portfolio clearly reflects strategic objectives.
 
Answer & Explanation Answer: D) To ensure that the relationship between projects in the portfolio clearly reflects strategic objectives.

Explanation:

There is not necessarily a relationship between projects in a portfolio. Answer D is actually one of the goals of PROGRAM management. PMBOK Guide [1.4]

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

Three partners shared the profit in a business in the ratio 4:6:8. They had partnered for 12 months, 8 months and 6 months respectively. What was the ratio of their investments?

A) 4:6:8 B) 4:7:8
C) 4:8:16 D) 4:9:16
 
Answer & Explanation Answer: D) 4:9:16

Explanation:

Let their investments be Rs. x for 12 months, Rs. y for 8 months and Rs. z for 6 months respectively.

Then, 12x : 8y : 6z = 4 : 6 : 8

Now, 12x/8y = 4/6   <=>   9x=4y   <=>   y=9x/4

And, 12x/6z = 4/8   <=>   4x=z     <=>    z=4x

Therefore, x : y: z  =  x : 9x/4: 4x  =  4 : 9 : 16

Report Error

View Answer Report Error Discuss

Filed Under: Partnership

Q:

A statistical method for identifying which factors may influence specific variables of a product or process under development or in production is called

A) cost benefit analysis. B) sensitivity analysis.
C) cost of quality analysis. D) design of experiments.
 
Answer & Explanation Answer: D) design of experiments.

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification