Q:
| A) weak matrix. | B) functional. |
| C) strong matrix. | D) composite. |
Answer: A) weak matrix.
Explanation:
Explanation:
“Weak matrices maintain many of the characteristics of a functional organization, and the project manager role is more that of a coordinator or expediter than that of a true project manager.”