0
Q:
A) Planned Value (PV) divided by Earned Value (EV) | B) Earned Value(EV) divided by Planned Value (PV) |
C) Project duration divided by Earned Value divided by Planned Value (Duration/(EV/PV)) | D) Earned Value (EV) minus Planned Value (PV) |
Answer: B) Earned Value(EV) divided by Planned Value (PV)
Explanation:
Explanation:
Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it’s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance.