Q:

An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?

A) Additional resources using the contingency fund B) Escalation approval to use contingency funding
C) Team overtime to meet schedule D) Corrective action based on causes
 
Answer & Explanation Answer: D) Corrective action based on causes

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

4 9992
Q:

The Plan-Do-Check-Act cycle can be used to plan and implement Service Management Processes:
How many times should each stage of the cycle be visited?

A) There should be a single Plan and Do, and then Check and Act should be carried out multiple times to Implement Continual Improvement B) There should be a single %n. then the Do-Check-Act cycle should be repeated multiple times to Implement Continual improvement
C) The entire cycle should be repeated multiple times to Implement Continual Improvement D) Each stage should be carried out once in the order Plan-Do-Check-Act
 
Answer & Explanation Answer: D) Each stage should be carried out once in the order Plan-Do-Check-Act

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: ITIL Certification

0 9917
Q:

Why should monitoring and measuring be used when trying to improve services?

A) To validate, direct, justify and intervene B) To validate, measure, monitor and change
C) To validate, plan, act and improve D) To validate, assign resources, purchase technology and train people
 
Answer & Explanation Answer: A) To validate, direct, justify and intervene

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: ITIL Certification

2 9698
Q:

Why are CPM, GERT, and PERT not considered sufficient to create a project schedule?

A) All three are tools and techniques of schedule development, not the actual schedule B) As mathemetical analysis tools, they simply provide the dates that are posible, and do not consider resource pool limitations
C) They are sufficient. Each calculates early and late start and finish dates for each activity D) They are Monte Carlo techniques used to provide what-if analysis for adverse external factors on a project
 
Answer & Explanation Answer: B) As mathemetical analysis tools, they simply provide the dates that are posible, and do not consider resource pool limitations

Explanation:

Answer A is tempting because it is true by definition, but Answer B is correct because it properly answers the question, in that these techniques do not take into account resource pool constraints. Answer C is incorrect because it provides possible early and late start and finish dates, but not the actual schedules. Answer D is incorrect because none of the the three are simulation techniques. 

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

2 9416
Q:

What layer in the TCP/IP stack is equivalent to the Transport layer of the OSI model?

A) Application B) Host-to-Host
C) Internet D) Network Access
 
Answer & Explanation Answer: B) Host-to-Host

Explanation:

The four layers of the TCP/IP stack (also called the DoD model) are Application/process, Host-to-Host, Internet, and Network Access. The Host-to-Host layer is equivalent to the Transport layer of the OSI model.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA - CISCO Certification

4 8789
Q:

Ambiguous jurisdiction is more common in a functional or weak matrix organization than a strong matrix or projectized organization. Why?

A) Projectized organizations tend to be large in size B) Conflict between a functional manager and a project manager is more common in a functional or weak matrix
C) Legal issues are more frequent in a functional or weak matrix organization D) Projectized and strong matrix organizations are the best companies for a project manager to work for due to less ambiguity in scope development.
 
Answer & Explanation Answer: B) Conflict between a functional manager and a project manager is more common in a functional or weak matrix

Explanation:

Answer A is incorect because it is not a correct statement and has nothing to do with ambiguous jurisdiction. Answer C is incorrect because ambiguous jurisdiction is not related to legal issues at a company. Answer D is incorrect because the statement is incorrect and is not related to ambiguous jurisdiction.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

1 8716
Q:

Which of the following is Not a Function?

A) Incident Management B) Technical Management
C) Service Desk D) Application Management
 
Answer & Explanation Answer: A) Incident Management

Explanation:
Report Error

View Answer Report Error Discuss

4 8627
Q:

Acknowledgments, sequencing , and flow control are characteristics  of which OSI layer?

A) Layer 2 B) Layer 3
C) Layer 4 D) Lawer 7
 
Answer & Explanation Answer: C) Layer 4

Explanation:

A reliable Transport layer connection uses acknowledgments to make sure all data is transmitted and received reliably. A reliable connection is defined by a virtual circuit that uses acknowledgments, sequencing, and flow control, which are characteristics of the transport layer.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA - CISCO Certification

1 8605