Q:

Projects come in all sizes and shapes. Many times, project managers must daw from their "toolbox" of processes, tools, or methodologies. How many knowledge areas are described in the Project Management Body of Knowledge ? 

A) 2 - core processes and facilitating processes B) 9
C) 5 - initiation, planning,execution,control, and closing D) 39
 
Answer & Explanation Answer: B) 9

Explanation:

Answer A is incorrect because it pertains to the processes. Answer C is incorrect because these are the five phases of a project. Answer D is incorrect because there are 39 processes, not knowledge areas.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 3317
Q:

Two connected routers are configured only with RIP routing. What will be the result when a router receives a routing update that contains a higher-cost path to a network already in its routing table?

A) The updated information will be added to the existing routing table B) The update will be ignored and no further action will occur
C) The updated information will replace the existing routing table entry D) The existing routing table entry will be deleted from the routing table and all routers will exchange routing updates to reach convergence
 
Answer & Explanation Answer: B) The update will be ignored and no further action will occur

Explanation:

When a routing update is received by a router, the router first checks the administrative distance (AD) and always chooses the route with the lowest AD. However, if two routes are received and they both have the same AD and differing metrics , then the router will choose the one route with the lowest metrics or , in RIP's case, hop count.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 3313
Q:

Copying the logs on the standby/backup server is an operation of Log Shipping

A) TRUE B) FALSE
Answer & Explanation Answer: A) TRUE

Explanation:

It is one of the operation of Log Shipping

Report Error

View Answer Workspace Report Error Discuss

0 3311
Q:

As part of trouble shooting errors in a VPN connection, what logs must be checked?

A) IPSec logging B) Event viewer
C) VPNSec Log D) All of above
 
Answer & Explanation Answer: A) IPSec logging

Explanation:
Report Error

View Answer Report Error Discuss

0 3309
Q:

What is the maximum number of IP addresses that can be assigned to hosts on a local subnet that uses the 255.255.255.224 subnet mask?

A) 15 B) 16
C) 30 D) 31
 
Answer & Explanation Answer: C) 30

Explanation:

A/27 (255.255.255.224) is 3 bits on and 5 bits off. This provides 8 subnets, each with 30 hosts. Does it matter if this mask is used with a Class A, B, or C network address? Not at all. The number of host bits would never change.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 3304
Q:

which IOS command enables access to high-level commands?

A) su root B) admin 0
C) enable D) init
 
Answer & Explanation Answer: C) enable

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: CCENT

1 3303
Q:

How can you assign a profit center to a sales order item?

A. The profit center is taken from the customer master record.
B. The profit center can be entered manually.
C. The profit center for the material is set automatically.
D. The profit center can be set with a substitution.

Answer

Answer : B , C , D

Report Error

View answer Workspace Report Error Discuss

Subject: SAP CO

1 3294
Q:

A Good CFO will tell you that it is important to look at your bottom line and determine how to increase profits for the organization. Veronica, the new CFO at a local university, is taking that approach and applying it to new projects. Therefore,she wants to include costs from each phase of the project on a total expenditure is known as 

A) An opportunity cost B) A sunk cost
C) NPV D) A life cycle
 
Answer & Explanation Answer: D) A life cycle

Explanation:

Life Cycle costing includes the costs from each phase of the project life cycle when the total investment costs are calculated. Answer A is incorrect because an opportunity cost is the difference between a chosen investment and the one that is passed up. Answer B is incorrect because sunk costs are costs that have been incurred and cannot be reversed. Answer C is incorrect because net present value (NPV) is the present value of cash inflows(benifits) minus the present value of cash outflows (costs).

Report Error

View Answer Report Error Discuss