A project in PMP can be defined as a :

A) Permanent endeavor that produces repetitive outputs B) Temporary endeavor undertaken to create a unique product, service, or result
C) Permanent endeavor undertaken to create a unique product, service, or result D) Temporary endeavor that produces repetitive outputs
 
Answer & Explanation Answer: B) Temporary endeavor undertaken to create a unique product, service, or result

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

17 3246
Q:

As part of trouble shooting errors in a VPN connection, what logs must be checked?

A) IPSec logging B) Event viewer
C) VPNSec Log D) All of above
 
Answer & Explanation Answer: A) IPSec logging

Explanation:
Report Error

View Answer Report Error Discuss

0 3245
Q:

Copying the logs on the standby/backup server is an operation of Log Shipping

A) TRUE B) FALSE
Answer & Explanation Answer: A) TRUE

Explanation:

It is one of the operation of Log Shipping

Report Error

View Answer Workspace Report Error Discuss

0 3235
Q:

Projects come in all sizes and shapes. Many times, project managers must daw from their "toolbox" of processes, tools, or methodologies. How many knowledge areas are described in the Project Management Body of Knowledge ? 

A) 2 - core processes and facilitating processes B) 9
C) 5 - initiation, planning,execution,control, and closing D) 39
 
Answer & Explanation Answer: B) 9

Explanation:

Answer A is incorrect because it pertains to the processes. Answer C is incorrect because these are the five phases of a project. Answer D is incorrect because there are 39 processes, not knowledge areas.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 3232
Q:

You use Microsoft Visual Studio 2010 and Microsoft .NET Framework 4 to create an application. You use the ADO.NET Entity Data Model (EDM) to define a Customer entity. You need to add a new Customer to the data store without setting all the customer's properties. What should you do?

A) Call the Create method of the Customer object. B) Call the CreateObject method of the Customer object.
C) Override the Create method for the Customer object. D) Override the SaveChanges method for the Customer object.
 
Answer & Explanation Answer: B) Call the CreateObject method of the Customer object.

Explanation:
Report Error

View Answer Report Error Discuss

17 3217
Q:

Project Cost Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Cost Control ?

Answer

I. Inputs



  • Cost baseline

  • Project funding requirements

  • performance reports

  • Work performance information

  • Approved change requests

  • Project management plan


II. Tools and Techniques



  • Cost change control system

  • Performance measurement analysis

  • Forecasting

  • Project performance reviews

  • Project management software 

  • Variance management


III. Outputs



  • Cost estimate (updates)

  • Cost baseline (updates)

  • Performance measurements

  • Forecasted completion

  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Project management plan (updates)


 

Report Error

View answer Workspace Report Error Discuss

0 3216
Q:

Project Procurement Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Contract Administration?

Answer

I. Inputs



  • Contract

  • Contract management plan

  • Selected sellers

  • Performance reports

  • Approved change requests

  • Work performance information


II. Tools and Techniques



  • Contract change control system

  • Buyer-conducted performance review

  • Inspections and audits

  • Performance reporting

  • Payment system

  • Claims administration

  • Records management system

  • Information technology


III. Outputs



  • Contract documentation 

  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Project management plan (updates)


                 - Procurement management plan


                 - Contract management plan

Report Error

View answer Workspace Report Error Discuss

0 3213
Q:

which IOS command enables access to high-level commands?

A) su root B) admin 0
C) enable D) init
 
Answer & Explanation Answer: C) enable

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: CCENT