Q:

Importance of project life cycle?

Answer

A project has a beginning and an end and passes through several phases of development known as life cycle phases. Every project has certain phases of development. A clear understanding of these phases allows managers and executives to maintain control of the project more efficiently.
These phases are varied depending upon the industry involved but all follow the same basic steps.


 


How Important is Project Life Cycle::


1. This is a tried and tested method for delivering projects on time, within budget and to the expected quality targets.


2. Aids communication and helps define roles within the project organisation as it provides a framework for the project that is visible and understood by all members of the project.


3. The project lifecycle will allow the project manager to link progress directly to each phase and recognise the completion of each phase


4. The phases within the project lifecycle provide an understanding of the evolution of the project, being able to identify areas that need greater attention at different times such as risk management in the early stages and more Project Evaluation Reviews during the Implementation stage.


5. At each stage, approval is generally required from outside the project team before proceeding to the next stage.


6. The project life cycle also allows for the gate procedure to be used.


7. At each stage, approval is generally required from outside the project team before proceeding to the next stage.

Report Error

View answer Workspace Report Error Discuss

11 2778
Q:

Which statement fragments a table as round robin?

A) FRAGMENT AS ROUND ROBIN IN dbspace 1, dbspace 2 B) FRAGMENT BY ROUND ROBIN IN dbspace1, dbspace 2
C) FRAGMENT TABLE BY ROUND ROBIN IN dbspace1, dbspace 2 D) FRAGMENT BY ROUND ROBIN
 
Answer & Explanation Answer: B) FRAGMENT BY ROUND ROBIN IN dbspace1, dbspace 2

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: IBM Certification

2 2777
Q:

You move a file from an NTFS volume on a Windows 2000 client computer to a folder on an NTFS volume on a Windows 2000 Server computer. What effect does moving this file have on the  NTFS permissions assigned to the file?

A) The moved file retains all of its original NTFS permissions B) The moved file loses all of its original NTFS permissions, and now has no permissions.
C) The moved file loses some of its original NTFS permissions, and inherits some of the NTFS permissions from its destination folder D) The moved file loses all of its original NTFS permissions, and inherits all of the inheritable NTFS permissions from its destination folder
 
Answer & Explanation Answer: D) The moved file loses all of its original NTFS permissions, and inherits all of the inheritable NTFS permissions from its destination folder

Explanation:

When a file or folder is moved to a new folder on a different volume, it inherits all of the inheritable NTFS permissions from the destination folder.

Report Error

View Answer Report Error Discuss

0 2773
Q:

[CO-OM-CEL] Expenses in financial accounting that are relevant to cost accounting are recorded in Controlling using :

A. Secondary expenses elements

B. Primary cost elements

C. Primary expenses elements

D. Secondary cost elements

Answer

Answer : B

Report Error

View answer Workspace Report Error Discuss

Subject: SAP CO

1 2770
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Activity Definition ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Project management plan


II. Tools and Techniques



  • Decomposition

  • Templates

  • Rolling wave planning

  • Expert judgment

  • Planning component


III. Outputs



  • Activity list

  • Activity attributes

  • Milestone list

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 2768
Q:

Why should you use the Ad Preview and Diagnosis tool to check if your ads are live and running on Google?

Answer

By searching for keywords that trigger your ad, you can rack up impressions without clicks, which may lower your Click-Through Rate, which may prevent your ad from appearing as often as it is eligible.

Report Error

View answer Workspace Report Error Discuss

0 2767
Q:

Suppose a customer is planning to create a non-hosted Linux partition on an i825. Linux will have only direct-attach devices. What is the Linux console option?

A) Use OS/400 VNC support. B) Telnet to the virtual console.
C) Share the primary partitions console. D) Allocate a console IOA to the Linux partition.
 
Answer & Explanation Answer: B) Telnet to the virtual console.

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: IBM Certification

1 2760
Q:

Project Procurement Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Plan Contracting?

Answer

I. Inputs



  • Procurement management plan

  • Contract statement of work

  • Make-or-buy decisions

  • Project management plan


                 - Risk register


                 - Risk related contractual agreements


                 - Resource requirements


                 - Project schedule


                 - Activity cost estimate


                 - Cost baseline


II. Tools and Techniques



  • Standard forms

  • Expert judgment


III. Outputs



  • Procurement documents

  • Evaluation criteria

  • Contract statement of work (updates)

Report Error

View answer Workspace Report Error Discuss