Q:

Which one of the following elements will be an isobar of calcium if the atomic number of calcium is 20 and its mass number is 40?

 

A) Element with 18 neutrons and 20 protons  B) Element with 19 neutrons and 18 protons 
C) Element with 19 neutrons and 20 protons  D) Element with 18 neutrons and 22 neutrons
 
Answer & Explanation Answer: D) Element with 18 neutrons and 22 neutrons

Explanation:
Isobar: one of two or more atoms having equal atomic weights but different atomic numbers.
 
                    Mass number     Electrons      Neutrons
    Calcium            40                    20                 20
 
     Argon              40                    18                 22
Report Error

View Answer Report Error Discuss

Filed Under: Chemistry
Exam Prep: Bank Exams

0 2280
Q:

Buckingham palace became the official royal residence during the reign of which British monarch?

A) Queen Victoria B) King George III
C) King Henry VIII D) King George V
 
Answer & Explanation Answer: A) Queen Victoria

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: World History

1 2280
Q:

The IMBEX 2018-19 started between India and which country?

A) Afghanistan B) Myanmar
C) China D) Nepal
 
Answer & Explanation Answer: B) Myanmar

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: World Geography
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO

2 2280
Q:

What can you expect if you raise your bids?

Answer

More conversions and a higher CPA, in general.

Report Error

View answer Workspace Report Error Discuss

0 2280
Q:

How many budgets are presented in the Parliament?

A) 91 B) 92
C) 90 D) 89
 
Answer & Explanation Answer: D) 89

Explanation:

Till now, upto 2019 89 budgets are presented in Parliament.

Report Error

View Answer Report Error Discuss

Filed Under: Indian History
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

5 2280
Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Develop Preliminary Project Scope Statement phase?

Answer

I. Inputs



  • Project Charter

  • Project Statement of work

  • Enterprise environmental factors

  • Organizational process assets


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Preliminary project scope statement 

Report Error

View answer Workspace Report Error Discuss

0 2279
Q:

Project Procurement Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Plan Purchase and Acquisitions?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Project management plan


                 - Risk register


                 - Risk - related contractual agreements


                 - Resource requirements


                 - Project schedule


                 - Activity cost estimates


                 - Cost baseline


II. Tools and Techniques



  • Make-or-buy analysis

  • Expert judgement

  • Contract types


III. Outputs



  • Procurement management plan

  • contract statement of work

  • make-or-buy decisions

  • Requested changes       

Report Error

View answer Workspace Report Error Discuss

0 2279
Q:

In the fig. ABC is inscribed in a circle with centre O. If ∠ABC = 30° then ∠ACB is equal to

A) 30° B) 60°
C) 50° D) 90°
 
Answer & Explanation Answer: B) 60°

Explanation:
Report Error

View Answer Report Error Discuss

0 2279