Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Integrated Change Control Phase?

Answer

I. Inputs



  • Project management plan

  • Requested changes

  • Work performance information

  • Recommended preventive actions

  • Recommended corrective actions

  • Recommended defect repair

  • Deliverables


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Approved change requests

  • Rejected change requests

  • Project management plan(updates)

  • Project scope statement (updates)

  • Approved corrective actions

  • Approved preventive actions

  • Approved defect repair

  • Validated defect repair

  • Deliverables 

Report Error

View answer Workspace Report Error Discuss

0 2450
Q:

Complete the analogy 3 : 11 :: 7 : ___

A) 29 B) 18
C) 24 D) 51
 
Answer & Explanation Answer: D) 51

Explanation:
Report Error

View Answer Report Error Discuss

4 2450
Q:

Project Management Processes

What is the underlying concept for the interaction among the project management processes?

Answer

Plan-do-check-act cycle

Report Error

View answer Workspace Report Error Discuss

0 2449
Q:

Planning Process Group

What are the Project Management Processes included in the Planning Process Group?

Answer



      • Develop Project Management Plan

      • Scope Planning

      • Scope Definition

      • Create WBS

      • Activity Definition

      • Activity Sequencing

      • Activity Resource Estimating

      • Activity Duration Estimating

      • Schedule Development

      • Cost Estimating

      • Cost Budgeting

      • Quality Planning

      • Human Resource Planning

      • Communications Planning

      • Risk Management Planning

      • Risk Identification

      • Qualitative Risk Analysis

      • Quantitative Risk Analysis

      • Risk Response Planning

      • Plan purchases and Acquisitions

      • Plan Contracting



Report Error

View answer Workspace Report Error Discuss

0 2449
Q:

Choose the correctly spelt word:-

A) Gragarious B) Gragerious
C) Gregarious D) Grigareous
 
Answer & Explanation Answer: C) Gregarious

Explanation:

Gregarious is spelt correctly which means sociable.

Report Error

View Answer Report Error Discuss

Filed Under: English
Exam Prep: Bank Exams

0 2449
Q:

Term ‘Visible Horizon’ in astronomy is defined as:-

A) The circle of contact of the earth and the cone of visual rays passing through the meridian of the place. B) The circle of contact of the earth and the cone of visual rays not passing through the meridian of the place.
C) The circle of contact of the earth and the cone of visual rays passing through the point of observation. D) The circle of contact of the earth and the cone of visual rays not passing through the point of observation.
 
Answer & Explanation Answer: C) The circle of contact of the earth and the cone of visual rays passing through the point of observation.

Explanation:

Visible Horizon is the circle of contract, with the earth, of the cone of visual rays passing through the point of observation.

Report Error

View Answer Report Error Discuss

Filed Under: General Science
Exam Prep: Bank Exams

0 2449
Q:

The magnitude of buoyant force depends on the .......... of the fluid.

A) mass B) temperature
C) volume D) density
 
Answer & Explanation Answer: D) density

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Physics
Exam Prep: AIEEE , Bank Exams , GATE

1 2449
Q:

Which country bagged Award of Excellence for 'Best in Show' at New York Times Travel Show 2019 ?

A) China B) England
C) India D) Japan
 
Answer & Explanation Answer: C) India

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

0 2448