Q:
| A) is not one of the inputs to these processes. | B) is used to allocate the project budget to the various project activities. |
| C) is used to assign costs to the time period when the costs will be incurred | D) is used to determine the size of the contingency component of the budget after all scheduled costs are accounted for. |
Answer: C) is used to assign costs to the time period when the costs will be incurred
Explanation:
Explanation:
“This [project schedule] information can be used to aggregate costs to the calendar periods when the costs are planned to be incurred.” PMBOK [7.2.1.4]