Q:
A) Core process take more time and resources | B) Core processes are performed in the same sequence and facilitating processes are intermittent |
C) Facilitating processes often require micromanagement in order to be completed on time | D) Core Processes are not performed in the same sequence and facilitating processes are |
Answer: B) Core processes are performed in the same sequence and facilitating processes are intermittent
Explanation:
Explanation:
Answer A is incorrect because the core processes do not necessarily take more time and resources than facilitating processes. Answer C is incorrect because core processes are not usually tied with micromanagement of tasks. Answer D is incorrect because core processes are performed in the same sequence on most projects.