Q:

Iam looking to estimate the cost on a project, but I don't want to spend a lot of time on a  detailed analysis. I really want a ballpark figure. What options do I have?

A) None - Cost estimating requires details to be accurate B) Use the cost of similar projects
C) Use a rule-of-thumb or per-square-foot estimate D) Add up the costs on the WBS
 
Answer & Explanation Answer: B) Use the cost of similar projects

Explanation:

Although it is less accurate than adding up individual costs from the WBS, it is less time consuming. The trade-off is accuracy. Answer A is incorrect because to do a more accurate cost estimate, you need to delve into details. Answer C is tempting also, and possible, except we don't really know if the project in question can use perametric modeling . Answer D is incorrect because it takes the most time, but it is most accurate.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4313
Q:

Why are risk tolerances and thresholds important to identify in the risk management Plan?

A) Tolerances and thresholds, when documented, can help to define the target by which the project team can measure the effectiveness of the risk response plan execution B) Tolerances and thresholds help to define how often the risk management process will be performed
C) Tolerances and thresholds determine what tools and data sources will be used in risk management D) Tolerances and thresholds provide the basis for costing the risk management process as well as defining how risk activities will be recorded
 
Answer & Explanation Answer: A) Tolerances and thresholds, when documented, can help to define the target by which the project team can measure the effectiveness of the risk response plan execution

Explanation:

Answer B defines the timing that should be addressed in the risk management plan. Answer C defines the methodology that should be identified in a risk management plan. Answer D touches on the budgeting and tracking that should be defined in the risk management plan.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4055
Q:

Go command is a signal to execute the entire batch of SQL statements after previous Go

A) TRUE B) FALSE
Answer & Explanation Answer: A) TRUE

Explanation:
Report Error

View Answer Workspace Report Error Discuss

0 3103
Q:

Copying the logs on the standby/backup server is an operation of Log Shipping

A) TRUE B) FALSE
Answer & Explanation Answer: A) TRUE

Explanation:

It is one of the operation of Log Shipping

Report Error

View Answer Workspace Report Error Discuss

0 2712
Q:

Multiple users can share a local temporary table

A) TRUE B) FALSE
Answer & Explanation Answer: B) FALSE

Explanation:

Multiple users can't share a local temporary table

Report Error

View Answer Workspace Report Error Discuss

0 2979
Q:

STUFF and REPLACE are used to replace characters in a string

A) TRUE B) FALSE
Answer & Explanation Answer: A) TRUE

Explanation:

They both are used to replace characters in a string

Report Error

View Answer Workspace Report Error Discuss

0 2517
Q:

Breaking of relationships is allowed once referential integrity on a database is enforced

A) TRUE B) FALSE
Answer & Explanation Answer: B) FALSE

Explanation:

Breaking of relationships is prevented once referential integrity on a database is enforced

Report Error

View Answer Workspace Report Error Discuss

0 3993
Q:

Can’t update primary table’s primary key if row being modified has related rows in secondary table once referential integrity is enforced

A) TRUE B) FALSE
Answer & Explanation Answer: A) TRUE

Explanation:
Report Error

View Answer Workspace Report Error Discuss

0 2940