Certification Questions

Q:

When a station sends a transmission to the MAC address ff : ff : ff : ff : ff : ff, what type of transmission is it?

A) Unicast B) Multicast
C) Anycast D) Broadcast
 
Answer & Explanation Answer: D) Broadcast

Explanation:

A transmission to the MAC address ff : ff : ff : ff : ff : ff is a broadcast transmission to all stations.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 5422
Q:

A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained is a part of which plan?

A) Project integration plan. B) WBS development plan.
C) Configuration management plan. D) Scope management plan.
 
Answer & Explanation Answer: D) Scope management plan.

Explanation:

“The work involved in performing the five processes of Project Scope Management is preceded by a planning effort by the project management team. This planning effort is part of the Develop Project Management Plan process, which produces a scope management plan that provides guidance on how project scope will be defined, documented, verified, managed, and controlled. The scope management plan may be formal or informal, highly detailed, or broadly framed, based upon the needs of the project.”

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

2 5401
Q:

What is the purpose of the DHCP server?

A - to provide storage for email
B - to translate URLs to IP addresses
C - to translate IPv4 addresses to MAC addresses
D - to provide an IP configuration information to hosts

Answer

Answer : D


Explanation:The main purpose of the DHCP server is to provide IP configuration parameters to hosts such as the default gateway, domain name, Domain Name System – DNS .

Report Error

View answer Workspace Report Error Discuss

Subject: CCNA

4 5392
Q:

The schedule performance index (SPI) is calculated as

A) Planned Value (PV) divided by Earned Value (EV) B) Earned Value(EV) divided by Planned Value (PV)
C) Project duration divided by Earned Value divided by Planned Value (Duration/(EV/PV)) D) Earned Value (EV) minus Planned Value (PV)
 
Answer & Explanation Answer: B) Earned Value(EV) divided by Planned Value (PV)

Explanation:

Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it’s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance. 

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 5388
Q:

How many non- overlapping channels are available with 802.11b?

A) 3 B) 12
C) 23 D) 40
 
Answer & Explanation Answer: A) 3

Explanation:

The IEEE 802.11b standard provides three non-overlapping channels.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

2 5364
Q:

The exhibit below shows the output of a show ip interface brief on a Cisco router.

r1#show ip interface brief

Serial0/0 does not respond to ping requests. What step would you take to resolve the problem?

A) Change ip address on Serial0/0 B) Enable the interface Serial0/0
C) Check the physical connection in Serial 0/0 D) The interface looks fine in status up, problem must be somewhere else
 
Answer & Explanation Answer: C) Check the physical connection in Serial 0/0

Explanation:

In order for an interface to work properly and respond to ping requests, both Status and Protocol must be up.

Report Error

View Answer Report Error Discuss

Filed Under: CCENT

1 5334
Q:

You have a reference computer that runs Windows 7.

You plan to deploy an image of the computer.

You create an answer file named answer.xml.

You need to ensure that the installation applies the answer file after you deploy the image. Which command should you run before you capture the image?

A) Imagex.exe /append answer.xml /check B) Imagex.exe /mount answer.xml /verify
C) Sysprep.exe /reboot /audit /unattend:answer.xml D) Sysprep.exe /generalize /oobe /unattend:answer.xml
 
Answer & Explanation Answer: D) Sysprep.exe /generalize /oobe /unattend:answer.xml

Explanation:
Report Error

View Answer Report Error Discuss

15 5321
Q:

One of the goals of management by objectives (MBO) is to ensure that objectives of one level within an organization are supportive of and aligned with the objectives of another level of the organization. This methodology has been popular within some organizations as they define their culture. Which of the following is not true about MBO?

A) It has a top-down orientation B) Corrective actions are not part of the process
C) You need to establish clear and achievable objectives D) MBO is a natural fit for Project Management
 
Answer & Explanation Answer: B) Corrective actions are not part of the process

Explanation:

Corrective actions are part of the process after establishing objectives and checking on the objectives. The next step is to take corrective actions. Answers A, C, D are true statements and therfore are incorrect for this question.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 5320