Certification Questions

Q:

Which of the following is usually not considered a goal of portfolio management?

A) To manage the effective and efficient use of resources. B) To balance the portfolio among incremental and radical investments.
C) To maximize the value of the portfolio by careful examination of candidate projects and exclusion of those no meeting strategic objectives. D) To ensure that the relationship between projects in the portfolio clearly reflects strategic objectives.
 
Answer & Explanation Answer: D) To ensure that the relationship between projects in the portfolio clearly reflects strategic objectives.

Explanation:

There is not necessarily a relationship between projects in a portfolio. Answer D is actually one of the goals of PROGRAM management. PMBOK Guide [1.4]

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4989
Q:

What is one way to limit a user's access to only a specific number of accounts in the MCC?

Answer

Create a new MCC account linked to the original MCC account. Move the specified number of accounts into that MCC and grant the user access to the sub-MCC account.

Report Error

View answer Workspace Report Error Discuss

33 4988
Q:

Convert 10100010111101011001110110001011 2 to dotted decimal.

Answer

Convert to dotted hexadecimal first, and then convert each hexadecimal number pair to decimal.

A2.F5.9D.8B then 162.245.157.139

Report Error

View answer Workspace Report Error Discuss

Subject: CCNP

14 4986
Q:

Assuming that the phases in a project are concept, development, implementation and termination, which phase typically has the highest degree of uncertainty?

A) Concept B) Development
C) Implementation D) Termination
 
Answer & Explanation Answer: A) Concept

Explanation:

The first phase in a project always has the greatest degree of uncertainty because at this point in time the product is the least well defined. PMBOK, See figure 2-2. [2.1.1]

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4976
Q:

There are three possible routes for a router to reach a destination network. The first route is from OSPF with a metric of 782. The second route is from RIPv2 with a metric of 4. The third is from EIGRP with a composite metric of 20514560. Which route will be installed by the router in its routing table?

A) RIPv2 B) EIGRP
C) OSPF D) All three
 
Answer & Explanation Answer: B) EIGRP

Explanation:

Only the EIGRP routes will be placed in the routing table because it has the lowest administrative distance (AD), and that is always used before metrics.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

1 4973
Q:

Suppose you have a customer who has a central HQ and six branch offices. The customer anticipates adding six more branches in the near future. It  whishes to implement  a WAN technology that will allow the branches to economically connect to HQ and you have no free ports on the HQ router. which of the following would you recommend?

A) PPP B) HDLC
C) Frame Relay D) ISDN
 
Answer & Explanation Answer: C) Frame Relay

Explanation:

The key is "there are no free ports" on your router. Only Frame Relay can provide a connection to multiple locations with one interface, and in an economical manner no less.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 4943
Q:

What switch must be added to the ipconfig command on a PC to verify DNS configuration?

A) /dns B) -dns
C) /all D) -all
 
Answer & Explanation Answer: C) /all

Explanation:

The /all switch must be added to the ipconfig command on a PC to verify DNS configuration.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 4937
Q:

Why are risk tolerances and thresholds important to identify in the risk management Plan?

A) Tolerances and thresholds, when documented, can help to define the target by which the project team can measure the effectiveness of the risk response plan execution B) Tolerances and thresholds help to define how often the risk management process will be performed
C) Tolerances and thresholds determine what tools and data sources will be used in risk management D) Tolerances and thresholds provide the basis for costing the risk management process as well as defining how risk activities will be recorded
 
Answer & Explanation Answer: A) Tolerances and thresholds, when documented, can help to define the target by which the project team can measure the effectiveness of the risk response plan execution

Explanation:

Answer B defines the timing that should be addressed in the risk management plan. Answer C defines the methodology that should be identified in a risk management plan. Answer D touches on the budgeting and tracking that should be defined in the risk management plan.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification