Q:

The software development life cycle begins with a proof of concept and progress into the build, test, and acceptance phases as the project develops. Some times, differences between stakeholders can develop into conflict, which impacts the customer. As a trained, professional project manager, how do you handle this situation and resolve the customer's concerns?

A) Let the customer vent and take notes B) Schedule a meeting
C) Develope a change request for the customer D) Resolve the matter in favour of the customer
 
Answer & Explanation Answer: D) Resolve the matter in favour of the customer

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4457
Q:

George is very open with his team members. He invites questions and discussion, and encourages new suggestions and ideas. He considers all this carefully before making any but the most minor project decisions, but ultimately chooses the course he personally believes is the right one. His leadership style is best characterized as

A) Democratic B) Consultative
C) Participative D) Benevolent
 
Answer & Explanation Answer: C) Participative

Explanation:

The Participative leadership style is characterized by 1) allowing a great deal of freedom in identifying problems and solutions, 2) working closely with subordinates, 3) allows extensive participation, but 4) reserving to him/herself the final decision. The consultative style is not so open, with discussion more focused around the leader’s uncertainties than asking for new ideas.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4457
Q:

Which screen area(s) in the transaction for goods movements MIGO cannot be closed?

A. Item overview

B. Header data

C. Overview tree

D. Detail data for item

Answer

Answer : A


 


Explanation: Excluding the item overview, you can open and close all screen  areas
individual ly in the MIGO transaction.

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

3 4450
Q:

What command do you type to save the configuration stored in RAM to NVRAM?

A) Router (config) #copy current to starting B) Router #copy starting to running
C) Router (config) #copy running - config startup - config D) Router#copy run start
 
Answer & Explanation Answer: D) Router#copy run start

Explanation:

To copy the running - config to NVRAM so that it will be used if the router is restarted , use the copy running-config startup-config command in privileged mode (copy run start for short).

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

0 4426
Q:

An important tool for project scope management is

A) Fast tracking B) Work breakdown structure
C) Crashing D) A Gantt Chart
 
Answer & Explanation Answer: B) Work breakdown structure

Explanation:

Work breakdown structure is an important tool for project scope management.

 

Project Scope Management refers to the set of processes that ensure a project’s scope is accurately defined and mapped. Scope Management techniques enable project managers and supervisors to allocate just the right amount of work necessary to successfully complete a project—concerned primarily with controlling what is and what is not part of the project’s scope.

Report Error

View Answer Report Error Discuss

14 4425
Q:

Which of the following statements about VPRS(cost) are correct?

A. It is controled by the customer master

B. A condition type VPRS is a statistical condition type

C. A condition record can be created for a condition type VPRS (cost)

D. It is controled by the material master

Answer

Answer : B

Report Error

View answer Workspace Report Error Discuss

Subject: SAP SD

2 4399
Q:

Customer Perceptions and Business Outcomes help to define what ?

A) Key Performance Indicators (KPI's) B) Service Value
C) Total Cost of Ownership (TCO) D) Governance
 
Answer & Explanation Answer: B) Service Value

Explanation:
Report Error

View Answer Report Error Discuss

6 4398
Q:

Initiating Process Group

What are the Project Management Processes included in the Initiating  Process Group ?

Answer


    • Develop Project Charter

    • Develop Preliminary Project Scope Statement


Report Error

View answer Workspace Report Error Discuss