Certification Questions

Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Schedule Control ?

Answer

I. Inputs



  • Schedule management plan

  • Schedule baseline

  • Performance reports

  • Approved change requests


II. Tools and Techniques



  • Progress reporting

  • Schedule change control system

  • Performance measurement

  • Project management software

  • Variance analysis

  • Schedule comparision bar charts


III. Outputs



  • Schedule model data (updates)

  • Schedule baseline (updates)

  • Performance measurements

  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Activity list (updates)

  • Activity attributes (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2227
Q:

Project Human Resource Management

What are the Project Management Processes included in the Project Human Resource Management?

Answer

Human Resource Planning - Identifying and documenting Project roles, responsibilities, and reporting relationships, as well as creating the staffing management plan.


Acquire Project Team - Obtaining the human resources needed to complete the project


Develop Project Team - Improving the competencies and interaction of team members to enhance project performance.


Manage Project Team - Tracking team member performance, providing feedback, resolving issues, and coordinating changes to enhance project performance.

Report Error

View answer Workspace Report Error Discuss

0 2221
Q:

For employees who do not use time recording, actual times for processing type M can also be recorded using the ... infotype.

A. Interval

B. Wage

C. Identity

D. Overtime

Answer

Answer : D

Report Error

View answer Workspace Report Error Discuss

Subject: SAP HR

0 2221
Q:

Before you can create cost centers, you must first create a _______ heirarchy.

A. Logical

B. Optimum

C. Complete

D. Standard

Answer

Answer : D

Report Error

View answer Workspace Report Error Discuss

Subject: SAP CO

0 2220
Q:

A large CRM project took place last year included hundreds of meetings between the various key users. All of the conversations were save in a single Word 2010 document. You need to find all instances of the following words 'bleed' and 'bled'. Which of the following wildcard searches would be best?

A) ble{2}d B) ble{1,}d
C) ble{e2}d D) ble[e2]d
 
Answer & Explanation Answer: B) ble{1,}d

Explanation:
Report Error

View Answer Report Error Discuss

2 2218
Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope control ?

Answer

I. Inputs



  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Project scope management plan

  • Performance reports

  • Approved change requests

  • Work performance information


II. Tools and Techniques



  • Change control system

  • Variance analysis

  • Replanning

  • Configuration management system


III. Outputs



  • Project scope statement(updates)

  • Work breakdown structure(updates)

  • WBS dictionary (updates)

  • Scope baseline (updates)

  • Requested changes

  • Recommended  corrective action

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2211
Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Qualitative Risk Analysis?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement 

  • Risk management plan

  • Risk register


II.  Tools and Techniques



  • Risk probability and impact assesment

  • Probability and impact matrix

  • Risk data quality assessment

  • Risk categorization 

  • Risk Urgency assessment


III. Outputs



  • Risk register (updates)

Report Error

View answer Workspace Report Error Discuss

0 2205
Q:

You want to move the Philadelphia OU from the acme1.com domain to the acme2.com domain. Which tool should you use?

A) MoveTree.exe B) The move command -line utility
C) Server Extensions Administrator D) Active Directory Domains and Trusts
 
Answer & Explanation Answer: A) MoveTree.exe

Explanation:

Use MoveTree.exe to move Active Directory objects from one domain to another.

Report Error

View Answer Report Error Discuss

0 2202